Road Construction Updates

Road Construction Updates   
                    
Click here for current traffic restrictions

CIP Hotline: (623) 876-4615

                           

Construction Zones Map

Project No.: PW19-ST01
Project Title: A Street Reconstruction Project

Project Scope:

This project would include the full reconstruction of "A" Street between Thunderbird Road and Meyer Lane. The proposed project would remove and replace approximately 2,000 linear feet of full pavement section, repair or replace any broken or inadequate curb and/or any sidewalks as well as updating ADA ramps to current standards. 

Current Status: New ramps at M Lane and Myer Lane have been poured. A Street has been paved and utility adjustments are in progress. The project is anticipated to be complete in mid November.
Website:
Traffic Control / Detours:  Click here for traffic restrictions
Project No.: EM17-ST01
Project Title: Butler Drive Improvement Project
Project Scope: Butler Drive is a 1/2 mile long collector street that serves a number of industrial businesses between El Mirage Road and the 127th Avenue alignment. The project will include removing and replacing the existing roadway with a 36-foot wide pavement section, installing new water service lines and evaluating the existing fire hydrant spacing along this corridor. MCDOT will extend Butler Drive from 127th Avenue to Dysart Road as part of a future phase of the Northern Parkway project.
Current Status: The asphalt has been completed, the signage has been installed and the utilities have been adjusted.  A preliminary punch list has been provided to the Contractor.                                                
Website:
Traffic Control / Detours:  Click here for traffic restrictions
Project No.: EM18-W02
Project Title: Dysart Road Water Line Project
Project Scope: In order to promote development in the square mile between Peoria Avenue, El Mirage Road, Olive Avenue and Dysart Road, the City proposes the installation of approximately 6,000 linear feet of 12-inch ductile iron water main in Dysart Road from Dysart High School to Joe R. Ramirez Road. The main will be stubbed to the east and west for future extensions. This work will be done in partnership with John F. Long Properties, LLLP, the property owner of much of the land within this area.  
Current Status: Water main and service lines have been installed between Dysart High School and south of Wolfley Drive.  Installation and testing will continue south through the end of the year.                                         
Website:
Traffic Control / Detours  Click here for traffic restrictions
Project No.: EM18-ST01
Project Title: Dysart Road Future Road Project

Project Scope:

Dysart Road is a roadway of regional significance but currently only has one lane in each direction south of Peoria Avenue. The City proposes to widen this corridor to 5 lanes with bike lanes and curb and gutter.  

Current Status: 30% plans and cost estimates have been completed.  Plans and cost estimates will be provided to MCDOT for review. 
Website:  
Traffic Control / Detours   
Project No.: ADOT
Project Title: Grand Ave Frontage Road Project
Project Scope: The Arizona Department of Transportation (ADOT) will lead this project along Grand Avenue. Phase II will include the reconstruction of the Frontage Road from Thunderbird Road to Greenway Road. The design of the project has been identified for funding through ADOT using MAG/Federal funds identified for Grand Avenue Phase II. The Transportation Policy Committee (TPC) included this project as part of the Regional Freeway and Highway Program's 2016 rebalancing pool to address the program surplus in FY 2026. The TPC has recommended a project budget not to exceed $6 million for this effort.
Current Status: The existing asphalt along the south side of the road has been completed.  Underground electrical work and hardscape grading continues.  The installation of curb and gutter has started.                         
Website: www.azdot.gov/projects/US60FrontageRd
Traffic Control / Detours  Click here for traffic restrictions
Project No.: EM16-ITS01
Project Title: I.T.S. Project
Project Scope: The scope of this project is to place fiber optic cable within existing conduit that will be installed along El Mirage Road and Thunderbird Road as part of other projects.  This cable will allow for the interconnection of seven traffic signals and five CCTV cameras along El Mirage Road  between Olive Avenue and Thunderbird Road. The goal of this infrastructure is to increase safety and enhance mobility along two of the most heavily traveled arterials within the City. The majority of this project will be funded via a Congestion Mitigation and Air Quality (CMAQ) grant from the Maricopa Association of Governments (MAG).
Current Status: Force account repairs to conduit have been completed.  Fiber is anticipated to arrive in early November and installation to start in mid November.                                                                               
Website:
Traffic Control / Detours  
Project No.: MCDOT
Project Title: Northern Parkway Future Road Project
Project Scope: Northern Avenue is to be widened into an expressway/parkway configuration as a road of regional significance.  The total project cost is currently estimated at $228 million. Costs include Design Concept Report, design, ROW acquisition, and construction shared between project partners El Mirage, Glendale, Peoria, Maricopa County, and MAG regional funding with construction scheduled over the next several years. In accordance with the IGA approved by Council on 6/26/08, the City share of the project is $9.5 million.
Current Status: Phase II (Dysart Rd to 111th Ave): County Board approved award of project. Anticipated start is December 2018. 
Overpasses (El Mirage Road OP & Dysart Road OP):  Combined 95% plans anticipated in November. 
El Mirage Alternative Access (Butler & 129th): Stakeholders reviewed Design SOQ's and provided scores to MCDOT.                                                                                     
Website: http://apps.mcdot.maricopa.gov/Projects/northern-parkway.aspx
Traffic Control / Detours   
Project No.: EM18-ST04
Project Title: Thunderbird Road Access Modification Project
Project Scope: This project will provide full access to the east driveway entrance to Casa Mirage Apartments located on the south side of Thunderbird Road between El Mirage Road and Primrose Street.
Current Status: A Traffic Study was prepared to review access alternatives. An alternative has been chosen and a proposal from a design consultant is currently under review by City staff.                         
Website: